HVAC
North Herts leisure heat pump programme given 30 April 2027 completion date
Salix Finance says gas boilers have been replaced with air source heat pumps at three North Hertfordshire leisure centres, with works at Letchworth resumed after Distribution Network Operator delays and a completion date of 30 April 2027.
North Hertfordshire Council's programme to replace gas boilers with air source heat pumps at three leisure centres has a completion date of 30 April 2027, Salix Finance said on 20 November, with works at Letchworth recently resumed after delays with the Distribution Network Operator.
Salix, which delivers the Public Sector Decarbonisation Scheme (PSDS), said the council secured £7.7m through the scheme for Royston Leisure Centre, North Herts Leisure Centre in Letchworth and Hitchin Swimming Centre. It gave the total project value as £9.2m.
The council's own pages describe a wider £16.4m programme at the three centres, part-funded by a £7.74m PSDS grant. That figure also covers leisure upgrades such as a gym extension and a refurbished changing village at Royston, where the council said it invested about £1.8m in improving facilities at the centre.
Sarah Kingsley, director of environment at North Hertfordshire Council, said: "We couldn't have delivered this project without Public Sector Decarbonisation Scheme funding."
She added: "The council has invested significant capital of its own, but this funding has been critical to making the project a success."
The plant replaced
According to Salix, North Herts Leisure Centre and Hitchin Swimming Centre had been running on 14-year-old gas boilers, while Royston Leisure Centre, which opened in 2005, had an 11-year-old boiler. All three have been replaced with air source heat pump systems.
Solar photovoltaic panels have been installed at Royston and at North Herts Leisure Centre, Salix said. The works also took a fabric-first approach, with insulation, double glazing and lighting upgrades across the sites.
Salix said the council's leisure centres account for 45% of its total carbon emissions. The upgrades are expected to save about 1,200 tonnes of carbon a year across the three sites, and the council anticipates a cut of around 60% in emissions from the centres themselves.
Programme progress
The council awarded the works contract to Willmott Dixon Construction Ltd in 2025. In June 2025 it said works would start that July and finish in spring 2026, and a spade-in-the-ground event was held at Royston Leisure Centre in July 2025, attended by representatives of the council, Willmott Dixon and the council's leisure operator partner, Everyone Active.
The council announced on 30 March 2026 that the Royston gym extension was complete and the gym had more than doubled in size. Salix said works at Royston are now finished, and membership there rose from 2,294 in April to 3,014 in October.
At Letchworth, Salix said works had recently resumed on site after delays with the Distribution Network Operator. Works at Hitchin Swimming Centre continue, and the council has said the Hitchin programme involved a partial weekday pool closure for around five months.
Salix gave the completion date for the whole programme as 30 April 2027. The council had said in June 2025 that works were planned to finish in spring 2026.
The funding
Phase 3 of the PSDS, worth £1.425bn, was launched by Salix. Under Phase 3c, the Department for Energy Security and Net Zero's register shows 209 public sector organisations were awarded grants for 244 heat decarbonisation and energy efficiency projects. Salix said Phase 3c projects can deliver across two financial years after the department granted an additional year of funding.
Salix said the programme supports the council's target of reaching net zero by 2030.
Kingsley said success over the next five to 10 years would be the three centres becoming examples for other local authorities considering similar decarbonisation projects. North Herts Leisure Centre has operated since 1982.
On the record: Willmott Dixon Construction Ltd, Everyone Active, Department for Energy Security and Net Zero
Sources
- Salix Finance (opens in a new tab) (accessed 2026-11-20)
- North Herts Council (opens in a new tab) (accessed 2026-11-20)
- North Herts Council (opens in a new tab) (accessed 2026-11-20)
- North Herts Council (opens in a new tab) (accessed 2026-11-20)
- North Herts Council (opens in a new tab) (accessed 2026-11-20)
- GOV.UK (Department for Energy Security and Net Zero) (opens in a new tab) (accessed 2026-11-20)
- Salix Finance (opens in a new tab) (accessed 2026-11-20)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.